99 WOOLNER AVE
InspectionLast refreshed on Apr 4, 2026
- Permit number
- 10 166886 BLD
- Permit type
- New Building · Other
- Applied
- 2010-04-30
- Issued
- 2010-06-16
Actions
Create monitor from this address
Report data issueOpens your email app with this record prefilled.Exact address alerts may depend on monitor support.
Timeline
Applied
2010-04-30
Issued
2010-06-16
Completed
Not available
Project description
To construct foundation and to install pre-fabricated metal structure for protection,control and telecomunication equipment for Hydro One.
Permit fields
- City area grid code
- W0539
- Current use
- Hydro One Substation
- Dwelling units created
- 0
- Dwelling units lost
- 0
- Estimated construction cost
- $400,000
- Industrial (use code)
- 80.32
- Proposed use
- Hydro One Substation
- Record created
- 2026-04-04T21:09:16.796591+00:00