150 SHERWAY DR
Revision 03: New 200mm watermain and water connection, including meter and check valve in accordance with City standards, which is located east of the existing Dorothy Ley Hospice Building (220 She…
Showing first 20 matching permits
Full count unavailable.
Sorted by most recent application date.
Alerts are not active until you save a monitor and add an email recipient.
Revision 03: New 200mm watermain and water connection, including meter and check valve in accordance with City standards, which is located east of the existing Dorothy Ley Hospice Building (220 She…
Proposal to install fire alarm devices for elevator recall in an existing hospital.
Proposal to install Maglock/Magnetic locks at the interior and exterior doors at new patient tower building, Central Utility Plan and Tunnel area.
Proposal for interior alterations to install prefabricated work room
Plumbing Revision 01 - Revised Water Meter Strategy for New Patient Tower with same scope as for revision to CUP & Tunnels permit (22-219525) submitted 26 August------------------------------------…
Rev 02: revised Water Meter Strategy. See cover letterRevision #01 - Revised Design of Circulation Tunnels linking the New Central Utility Plant (CUP), New Patient Tower and Existing Hospital.Plumb…
REV Drain - Proposal for Installation of new 200mm PVC Sanitary Sewer on East of McCall Building.Drain - Proposal for construction of new 9-storey Patient Tower,1-Storey Circulation Link connected …
2 Wall Sign for Trillium Hospital - 'ENTRANCE 6' & 'ENTRANCE 5'
2 Wall Signs*****Trilliam Health Centre in Etobicoke*****
Proposed demolition of existing Hospital Central Utility Plant (CUP) building- including services - and adjacent brick chimney and steel stack.
In accordance with OBC Sentences 3.8.3.13.(1) and (3), the shower within the washroom facility of each patient room of the proposed hospital building is required to be designed for barrier-free acc…
To erect and display 6 ground signs all displaying static copy.
Proposed installation and modification of overhead wet sprinkler system to accommodate the renovation of and existing interior hospital building space.
REVISION No. 04 for RETAINING WALL / PERMANENT CAISSON WALL EXTENSION TO ZONE PW3.REVISION 03: Construction of Shoring related to CUP & TunnelsRevision 02: Permanent caisson wall shoring design pac…
Architectural renovation/alteration of existing Nuclear Medicine Suite (incl. waiting room, washroom and staff area) into an MRI Suite, including associated waiting rooms, washroom and staff areas.…
Plumbing - Architectural renovation/alteration of existing Nuclear Medicine Suite (incl. waiting room, washroom and staff area) into an MRI Suite, including associated waiting rooms, washroom and s…
HVAC - Architectural renovation/alteration of existing Nuclear Medicine Suite (incl. waiting room, washroom and staff area) into an MRI Suite, including associated waiting rooms, washroom and staff…
REVISION 01: Civil / Site Services Scope related to CUP & Tunnels.Drain - Proposal for construction of new 9-storey Patient Tower,1-Storey Circulation Link connected to the eixsiting hospital build…
REVISION 03: Construction of Shoring related to CUP & TunnelsRevision 02: Permanent caisson wall shoring design package from shoring tradeRevistion 01: RESUBMISSION: SKETCHES FOR MINOR TOWER FOUNDA…
Revision #01 - Revised Design of Circulation Tunnels linking the New Central Utility Plant (CUP), New Patient Tower and Existing Hospital.Plumbing - Proposal for construction of New 2 storey Centra…
Page numbers are hidden until the total count is available from the data service.