185 NORTHWEST GT
Revision to TTC Vaughan Metropolitan Centre Station related to building permit 11-153001 BLD. Includes the aluminium and glass screen, complete with sliding doors and swing doors added along Grid L…
Showing first 20 matching permits
Full count unavailable.
Sorted by most recent application date.
Alerts are not active until you save a monitor and add an email recipient.
Revision to TTC Vaughan Metropolitan Centre Station related to building permit 11-153001 BLD. Includes the aluminium and glass screen, complete with sliding doors and swing doors added along Grid L…
FS - Sprinkler Shop Drawing - Spadina Subway Extension - Hwy 407 Station(Changes from original permit 10-243691)
Revision 01 - to mechanical layout for the Hwy 407 Station (Spadina Subway Extenstion)Plumbing - Spadina Subway Extension - Hwy 407 Station
Revision 2 - Eleven (11) mag lock devices have been removed from the bus terminal at Hwy 407 Station, two (2) mag locks remain at the south platfrom emergencey stairs (dwg A33-1) and north platform…
Revision 01 - to watermain connection to building, fire deptarment connection and hydrant locations for the Hwy 407 Station (Spadina Subway Extenstion)Drain - Spadina Subway Extension - Hwy 407 Sta…
Revision 01 - to mechanical layout for the Hwy 407 Station (Spadina Subway Extenstion)HVAC - Spadina Subway Extension - Hwy 407 Station
Revision 01 - to the Hwy 407 TTC station for the architectural, structural and fire alarm systemSpadina Subway Extension - Hwy 407 Station
Revision - to door number 400 - Implementation of 3 electromagnetic locking devices on two doors for purposes of access control. Installation is specified to meet the requirements subsection 3.2.4 …
Revision to floor layout of subway station and add new pedestrian tunnel - TTC VMC station Zoning process not required - in Vaughan
Revision to Fire protection for new TTC subway station. which includes changes to wet and dry stand pipe fire extinguisher locationss and clean agent systems.
Revision 01 - Various HVAC due to tunnel addition, duct re-routing, duct sized, AHU resizing and ACC/ACU deletionsHVAC - Spadina Subway Extension - Vaughan Corporate Centre Station.
Revision 01 - water connections revised and removed in some locations, storm sewer from STM MH 13 to STM MH 1 upsized from 150mm diameter to 200mm diameter, main entrance surface drainage design an…
Revision 01 - Various plumbing changes due to tunnel addition, water and drainage pipe rerouting and resizingPlumbing - Spadina Subway Extension - Vaughan Corporate Centre Station.
Revision 01-City of Toronto water metre relocated from Rm.423 to site chamber (backflow preventer type revised). A reduced pressue principle backflow preventer added for the irrigation system at th…
Revision 02 - City of Toronto water metre relocated from Rm.423 to site chamber (backflow preventer type revised). Removed water meter and backflow preventer from TTC substation mechanical room.Rev…
Revise as per plans. Install 2 electromagnetic locking devices.
Revision to HVAC - Subway Station with bus terminal and ancillary facilities at 185 Northwest Gate within the City of Toronto and 2800 Steeles Avenue West within City of Vaughan ( a.k.a Steeles Wes…
Revsion to Plumbing - Subway Station with bus terminal and ancillary facilities at 185 Northwest Gate within the City of Toronto and 2800 Steeles Avenue West within City of Vaughan ( a.k.a Steeles …
Deletion of fire protection cabinets at subway platform level.
OBC sentence 3.13.5.11.(5) requires that in addition to fire hose cabinets located such that every portion of the rapid transit station can be reached by a hose stream, hose stations shall be locat…