333 PROGRESS AVE
To construct a new building attached to existing paper machine building for operations meeting room, building 30'7x12.9, consists of poured foundation, steel fram structure with steel cladding, ste…
Showing first 11 matching permits
Full count unavailable.
Sorted by most recent application date.
Alerts are not active until you save a monitor and add an email recipient.
To construct a new building attached to existing paper machine building for operations meeting room, building 30'7x12.9, consists of poured foundation, steel fram structure with steel cladding, ste…
HVAC - To construct a new building attached to existing paper machine building for operations meeting room, building 30'7x12.9, consists of poured foundation, steel fram structure with steel claddi…
Proposed concrete base to hold tank and extension to house the scrubber.
Disconnect storm water from sanitary, directing water to an outlet to creek and installing a passive water filtration device
Fire alarm upgrade; modify existing fire alarm panel nomenclature
construct addition to bldg 'E', truck bay addition to "S", add 5 free-standing tanks and 3 roof top tanks
HVAC - construct addition to bldg 'E', truck bay addition to "S", add 5 free-standing tanks and 3 roof top tanks - Addition(s) Building 'E' - containing elecrtical switch gears and duct banks.
Plumbing - construct addition to bldg 'E', truck bay addition to "S", add 5 free-standing tanks and 3 roof top tanks - Addition(s) Buildin 'E' - containing elecrical switch gears and duct banks.
REINFORCED CONCRETE AND STEEL FRAMED ADDITION - BLDG. I
PARTIAL FOUNDATION
CONSTRUCT A NEW 1 STOREY BUILDING FOR THE PURPOSE OF WAREHOUSING AND PAPER MANUFACTURING - BLDG N