Relocation of existing storm sewers at West Ventilation Fan Plant (WVFP) and Tunnel Ventilation system Electric Building (TVSEB) at Kennedy Station
Showing first 17 matching permits
More may match beyond this page.
Sorted by most recent application date.
Alerts are not active until you save a monitor and add an email recipient.
Relocation of existing storm sewers at West Ventilation Fan Plant (WVFP) and Tunnel Ventilation system Electric Building (TVSEB) at Kennedy Station
Installation of three new catch basins and catch basin leads
Revision 01 - signal inverter room (105) no longer required. Faciitites design has been updated to refule the removal of the signal inverter room (105)New Service Rooms (east end platform level) ar…
Revision 01 - signal inverter room (105) no longer required. Faciitites design has been updated to refule the removal of the signal inverter room (105)Plumbing - New Service Rooms (east end platfor…
Revision 01 - signal inverter room (105) no longer required. Faciitites design has been updated to refule the removal of the signal inverter room (105)HVAC - New Service Rooms (east end platform le…
Plumbing - Traction Power Substation (TPSS) is required to supplement the traction power needed at Kennedy Station due to additonal trains travelling from Scarborough Centre Station to Kennedy Stat…
Traction Power Substation (TPSS) is required to supplement the traction power needed at Kennedy Station due to additonal trains travelling from Scarborough Centre Station to Kennedy Station. The TP…
HVAC - Traction Power Substation (TPSS) is required to supplement the traction power needed at Kennedy Station due to additonal trains travelling from Scarborough Centre Station to Kennedy Station.…
Plumbing - Construction of a new Ventilation Fan Plant west of Kennedy Station as part of the Scarborough Subway Extension
Drain - New Service Rooms (east end platform level) are required to provide space for the installation of SSE communications, signals, and power equipmentThe proposed scope includes construction of…
Plumbing - New Service Rooms (east end platform level) are required to provide space for the installation of SSE communications, signals, and power equipmentThe proposed scope includes construction…
HVAC - New Service Rooms (east end platform level) are required to provide space for the installation of SSE communications, signals, and power equipmentThe proposed scope includes construction of …
New Service Rooms (east end platform level) are required to provide space for the installation of SSE communications, signals, and power equipmentThe proposed scope includes construction of new ser…
Addition of Fire Detectors to support elevator automatic recall i.e., heat detectors at elevator landings excluding exterior landing, addition of heat detectors in elevator pits. Connection of elev…
Plumbing - interior alterations to 4 floors, platform level-add rooms, concourse-modify staff area with hvac & plb
HVAC - PROVIDE HVAC FOR ESCALATOR MAINTENANCE ROOM
PROVIDE HVAC FOR ESCALATOR MAINTENANCE ROOM